                            The original version of this paper was published here in May 2009:
                            See S-curve/intro.htm

                            This 4th Edition was submitted for publication in January 2019.
                            It is copyright © Midori Media.
                            Published here September 2019.

                            PART 2 | Worked Example | Generating Percentage S‑curves
                            Using Task Duration as a Quantity | PART 4

                            Worked Example

                            To better understand how S-curves are generated, consider a simple Project consisting of five Tasks. The first Task is a Summary Task, and thus must be ignored. The remaining four Tasks are Detail Tasks. Please note that although this worked example will only consider Man Hours, the calculations shown below are identical if Cost is used in lieu of Man Hours.

                            A Baseline Schedule prepared using MS Project for the example project is shown below.

                            Figure 9: Sample Baseline Schedule
                            Figure 9: Sample Baseline Schedule

                            Baseline Man Hours versus Time S‑curve

                            To generate a Baseline Man Hours versus Time S-curve, two sets of calculations are required.

                            The first set of calculations are performed for each Task in the Baseline Schedule.

                            (1)  Calculate the Duration in Days for each Task
                            Baseline Duration = Baseline Finish Date - Baseline Start Date + 1

                            (2)  Calculate Man Hours per Day for each Task
                            Baseline Man Hours per Day = Baseline Man Hours / Baseline Duration

                            These calculations are shown below.

                            Task Name

                            Baseline Start

                            Baseline Finish

                            Baseline Man Hours

                            Baseline Duration (1)

                            Baseline MH per Day (2)

                            Task No. 1

                            01‑Feb‑2016

                            02‑Feb‑2016

                            12.0

                            2

                            6

                            Task No. 2

                            02‑Feb‑2016

                            04‑Feb‑2016

                            24.0

                            3

                            8

                            Task No. 3

                            03‑Feb‑2016

                            04‑Feb‑2016

                            30.0

                            2

                            15

                            Task No. 4

                            04‑Feb‑2016

                            05‑Feb‑2016

                            24.0

                            2

                            12


                            Totals

                             

                             

                            90.0

                             

                             

                            Table 4: Baseline S‑curve Calculation 1 of 2

                            The second set of calculations are performed for each Day in the Baseline Schedule.

                            (3)  Calculate the total Man Hours per Day for all Tasks

                            (4)  Calculate the Year To Date Total for Man Hours per Day for all Tasks

                            These calculations are shown below.

                            Task / Date

                            01‑Feb‑2016

                            02‑Feb‑2016

                            03‑Feb‑2016

                            04‑Feb‑2016

                            05‑Feb‑2016

                            Task No. 1

                            6.0

                            6.0

                            --

                            --

                            --

                            Task No. 2

                            --

                            8.0

                            8.0

                            8.0

                            --

                            Task No. 3

                            --

                            --

                            15.0

                            15.0

                            --

                            Task No. 4

                            --

                            --

                            --

                            12.0

                            12.0


                            Totals per Day (3)

                            6.0

                            14.0

                            23.0

                            35.0

                            12.0


                            YTD Totals (4)

                            6.0

                            20.0

                            43.0

                            78.0

                            90.0

                            Table 5: Baseline S‑curve Calculation 2 of 2

                            The Baseline S-curve is constructed by assigning the Baseline dates to the X axis, and the Year To Date (YTD) values to the Y axis. The resulting Baseline Man Hours versus Time S‑curve is shown below.

                            Figure 10: Baseline Man Hours versus Time S-curve
                            Figure 10: Baseline Man Hours versus Time S‑curve

                            Please note that the Totals per Day values may be used to generate a Baseline Man Hours Histogram by assigning the dates to the X axis, and the Totals per Day values to the Y axis, as shown below.

                            Figure 11: Baseline Man Hours versus Time Histogram
                            Figure 11: Baseline Man Hours versus Time Histogram

                            Target Man Hours versus Time S‑curve

                            To generate the Actual and Target S-curves, a Production Schedule is required. For the purpose of this example, the Production Schedule will contain the same five Tasks (one Summary Task, four Detail Tasks) as the Baseline Schedule. Once again, the Summary Task must be ignored to ensure the calculations are accurate.

                            A Production Schedule for the example Project is shown below.

                            Figure 12: Sample Production Schedule
                            Figure 12: Sample Production Schedule

                            Note this schedule contains the Baseline data from the Production Schedule. This allows Baseline S‑curves to be generated from the Production Schedule.

                            To generate a Target Man Hours versus Time S‑curve, two sets of calculations are performed.

                            The first set of calculations are performed for each Task in the Production Schedule.

                            (1)  Calculate the Duration in Days for each Task
                            Duration = Finish Date - Start Date + 1

                            (2)  Calculate Man Hours per Day for each Task
                            Man Hours per Day = Man Hours / Duration

                            These calculations are shown below.

                            Task Name

                            Start

                            Finish

                            Man Hours

                            % Complete

                            Duration (1)

                            MH per Day (2)

                            Task No. 1

                            02‑Feb‑2016

                            03‑Feb‑2016

                            14.0

                            100%

                            2

                            7.0

                            Task No. 2

                            02‑Feb‑2016

                            05‑Feb‑2016

                            30.0

                            20%

                            4

                            7.5

                            Task No. 3

                            04‑Feb‑2016

                            06‑Feb‑2016

                            36.0

                            50%

                            3

                            12.0

                            Task No. 4

                            05‑Feb‑2016

                            07‑Feb‑2016

                            15.0

                            0%

                            3

                            5.0


                            Totals

                             

                             

                            95.0

                             

                             

                             

                            Table 6: Target S‑curve Calculation 1 of 2

                            Target Man Hours versus Time S-curve (Continued)

                            The second set of calculations are performed for each Day in the Production Schedule.

                            (3)  Calculate the total Man Hours per Day for all Tasks

                            (4)  Calculate the Year To Date Total for Man Hours per Day for all Tasks

                            These calculations are shown below.

                            Task / Date

                            01‑Feb-2016

                            02‑Feb-2016

                            03‑Feb-2016

                            04‑Feb-2016

                            05‑Feb-2016

                            06‑Feb-2016

                            Task No. 1

                            7.0

                            7.0

                            --

                            --

                            --

                            --

                            Task No. 2

                            7.5

                            7.5

                            7.5

                            7.5

                            --

                            --

                            Task No. 3

                            --

                            --

                            12.0

                            12.0

                            12.0

                            --

                            Task No. 4

                            --

                            --

                            --

                            5.0

                            5.0

                            5.0


                            Totals per Day (3)

                            14.5

                            14.5

                            19.5

                            24.5

                            17.0

                            5.0


                            Year to Date Total (4)

                            14.5

                            29.0

                            48.5

                            73.0

                            90.0

                            95.0

                            Table 7: Target S‑curve Calculation 2 of 2

                            The Target S-curve is constructed by assigning the dates to the X axis, and the Year To Date (YTD) values to the Y axis. The resulting Target Man Hours versus Time S‑curve is shown below.

                            Figure 13: Target Man Hours versus Time S-curve (Showing Baseline S‑curve For Comparison
                            Figure 13: Target Man Hours versus Time S‑curve (showing Baseline S‑curve for Comparison)

                            Please note that the Totals per Day values may be used to generate a Target Man Hours Histogram by assigning the dates to the X axis, and the Totals per Day values to the Y axis, as shown below.

                            Figure 14: Target Man Hours versus Time Histogram (Showing Baseline Histogram For Comparison)
                            Figure 14: Target Man Hours versus Time Histogram (showing Baseline Histogram for Comparison)

                            Actual Man Hours versus Time S-curve

                            To generate an Actual Man Hours versus Time S‑curve, two sets of calculations are performed. Before these calculations may be performed, the Cut Off Date needs to be defined. This is the date the Project's Tasks were last physically inspected to determine their % complete status. For this example a Cut Off Date of the 4th of February, 2016 will be used.

                            The first set of calculations are performed for each Task in the Production Schedule.

                            (1)  Determine the Task Status: Finished, In Progress, Not Started.
                            •  Finished: Tasks that have a Finish Date prior to the Cut Off Date.
                            •  In Progress: Tasks that have started and have a Finish Date on or after the Cut Off Date.
                            •  Not Started: Tasks that have a Start Date after the Cut Off Date.

                            (2)  Calculate the Duration to Date based on the Task Status.
                            •  Finished: Duration To Date = Finish Date - Start Date + 1
                            •  In Progress: Duration To Date = Cut Off Date - Start Date + 1
                            •  Not Started: Duration To Date = 0

                            (3)  Calculate Man Hours to Date for Finished and Ongoing Tasks.
                            Man Hours to Date = (Man Hours x % Complete) / Duration to Date

                            As discussed above in the Target S‑curve calculations, the total Task Man Hours to complete the Task are required.

                            In this worked example, the Production Schedule contains total Task Man Hours.

                            The required calculations are shown below.

                            Task Name

                            Start

                            Finish

                            Man
                             Hours

                            % Complete

                            Status (1)

                            Duration
                            to Date (2)

                            MH x % complete
                            Duration to Date (3)

                            Task No. 1

                            02‑Feb-2016

                            03‑Feb-2016

                            14.0

                            100%

                            Finished

                            2

                            7.0

                            Task No. 2

                            02‑Feb-2016

                            05‑Feb-2016

                            30.0

                            20%

                            In Progress

                            3

                            2.0

                            Task No. 3

                            04‑Feb-2016

                            06‑Feb-2016

                            36.0

                            50%

                            In Progress

                            1

                            18.0

                            Task No. 4

                            05‑Feb-2016

                            07‑Feb-2016

                            15.0

                            0%

                            Not Started

                            0

                            0.0


                            Totals

                            95.0

                            Table 8: Actual S-curve Calculation 1 of 2

                            The second set of calculations is performed for each Day in the Production Schedule up to the Cut Off Date.

                            (4)  Calculate the total Man Hours to Date per Day for all Tasks

                            (5)  Calculate the Year To Date Total for Man Hours to Date per Day for all Tasks

                            These calculations are shown below.

                            Task / Date

                            02‑Feb-2016

                            03‑Feb-2016

                            04‑Feb‑2016

                            05‑Feb-2016

                            06‑Feb-2016

                            07‑Feb-2016

                            Task No. 1

                            7.0

                            7.0

                            --

                            --

                            --

                            --

                            Task No. 2

                            2.0

                            2.0

                            2.0

                            --

                            --

                            --

                            Task No. 3

                            --

                            --

                            18.0

                            --

                            --

                            --

                            Task No. 4

                            --

                            --

                            --

                            --

                            --

                            --


                            Totals per Day (4)

                            9.0

                            9.0

                            20.0

                            --

                            --

                            --


                            YTD Totals (5)

                            9.0

                            18.0

                            38.0

                            --

                            --

                            --

                            Cut Off Date:   04-Feb-2016

                            Table 9: Actual S‑curve Calculation 2 of 2

                            The resulting Actual Man Hours versus Time S‑curve is shown in Figure 15.

                            Figure 15: Actual Man Hours versus Time S‑curve (showing Baseline S-curve for Comparison)
                            Figure 15: Actual Man Hours versus Time S‑curve (showing Baseline S‑curve for Comparison)

                            Please note that the Totals per Day values may be used to generate an Actual Man Hours Histogram by assigning the dates to the X axis, and the Totals per Day values to the Y axis, as shown in Figure 16.

                            Figure 16: Actual Man Hours versus Time Histogram (showing Baseline Histogram for Comparison)
                            Figure 16: Actual Man Hours versus Time Histogram (showing Baseline Histogram for Comparison)

                            The Baseline, Actual, and Target S-curves may be combined, as shown in Figure 17.

                            Figure 17: Man Hours versus Time S-curves
                            Figure 17: Man Hours versus Time S-curves
                            PART 2  PART 2

                            Home | Issacons | PM Glossary | Papers & Books | Max's Musings
                            Guest Articles | Contact Info | Search My Site | Site Map | Top of Page

                                                      Blog

                                                      Buy a car

                                                      Foreign exchange

                                                      Celebrity

                                                      Information

                                                      car

                                                      Mobile phone

                                                      education

                                                      Second-hand housing